UNIVERSITY
COLLEGE OF
LONDON
HOSPITAL.

AN INTEGRATED PROJECT NAVIGATING CENTRAL LONDON’S COMPLEX LOGISTICAL CHALLENGES.

CLIENT: UNIVERSITY COLLEGE LONDON HOSPITAL

STATUS: COMPLETE

LOCATION: TOTTENHAM COURT ROAD

Extensive demolition and excavation of a three-storey basement provides a new home to a Proton Beam Therapy unit helping hundreds of people fight cancer every year.

PROJECT OVERVIEW.

A fully integrated endeavour, the project encompassed environmental services, demolition, enabling works, and excavation of the basement box. The scheme needed a smart engineering approach as well as sensitive community liaison to leave a positive legacy.

PROJECT HIGHLIGHTS AND KEY STATS.
120,000m3 BASEMENT EXCAVATED & BUILT
55,000m3 OF MATERIAL EXCAVATED FROM SITE
800 Tonnes OF STEEL REQUIREMENTS SAVED THROUGH TEMPORARY WORKS DESIGN
360t OF TEMPORARY STEEL WORK USED
KEY ACHIEVEMENTS.

Sequential Programming to Preserve Party Walls
The potential for ground movement and sensitive party walls meant specific sequencing was required to protect the stability of the site. Our solution involved installation of huge steel props spanning 60m across site to facilitate the deep excavation.

Continuous Observation Saved on Steel
We simplified the temporary works design, resulting in a saving of 800t of temporary steelwork. Continuous supervision of the site with a traffic light hazard system allowed our scheme to remain safe without the extra steel. Not only was this a massive saving on carbon, but a cut to cost too.

Keeping Noise & Vibration to a Minimum
Working in central London often means working with several sensitive stakeholders, and this site was no different. Our community liaison and site team worked hard to minimise noise and vibration by creating an acoustic blanket, muffling sound to the adjacent hospital and student accommodation.

Working Four Metres Beneath Central London
To minimise the import of materials to site, the client asked us to begin piling from 4m below ground level. We created a simplified temporary works and underpinning system to enable this and used a CFA piling technique to further reduce disturbance to the neighbours.

THIS IS NO ORDINARY PROJECT: AS WELL AS BEING AN INNOVATIVE AND COMPLEX BUILD, THE FINISHED DEVELOPMENT WILL HAVE THE POTENTIAL TO IMPROVE AND EVEN SAVE THE LIVES OF THOSE SUFFERING WITH BLOOD DISORDERS AND COMPLEX CANCERS.
FABIENNE VIALA
CHAIRMAN OF BOUYGUES UK
KEY STAKEHOLDERS:

STRUCTURAL ENGINEER: BOUYGUES